Playground Progress

 

CITY MONEY:

As of October 10, 2000, City Manager John Bohenko said he has put $50,000 in the City Capital Plan for the Sherburne Playground.

If approved by City Council, the money will be available for July 1, 2001. Mr. Bohenko feels that it will be approved.

The city has control over purchase and design of the playground equipment. Mr. Bohenko said to me that he does not like where the equipment is right now, and will have city engineers come out in the Spring to evaluate the area and decide where the new equipment will be placed. Mr. Bohenko wants to move the location for the new equipment due to drainage problems, dangers posed by nearby trees and the close proximity to the highway.

Any money we raise through other means could be used toward other aspects of the park that have been suggested such as a picnic gazebo, benches, paved track around playground, and updating the basketball court--but all projects must approved by the City regardless of whether or not the City provides the funding.

We will be sending a letter to City Council before January 1 to encourage them to approve $50,000 for our park.

We hope to enlist volunteers from the Timberland Co. to assemble the playground, once approved by the City. This will cut the labor cost of installing the equipment saving us 30 percent of the estimated project cost. Maybe we could use this extra money for other equipment or other items for the park.

FUNDRAISING:

I have spoken to Nancy Clayburgh, who is the leader of PEP 2000. She is sending me a package to use as a reference for letters and fundraising ideas. She has offered her assistance to me if we should need it.

Please call Mr. Bohenko at (603) 431-2000 if you have any questions or comments.

Submitted by Lee Larusso, Playground Project Chair

 